Are you talking about automated unit/integration tests or manual tests?
For the former, my rule of thumb (based on measurements) is 40-50% added to development time i.e. if developing a use case takes 10 days (before an QA and serious bugfixing happens), writing good tests takes another 4 to 5 days - though this should best happen before and during development, not afterwards.